REC SILICON – MOLALA LAB

The project is a new, stand-alone, 11,400 Square Foot Research and Development Laboratory building on the Moses Lake Campus of REC Silicon. The building exterior is comprised of Composite Metal Panels offering the building a sleek and clean appearance. The interior is a mix of Laboratory areas and offices.

THE PROJECT CONTAINS SOME UNIQUE CHALLENGES WITH THE RELOCATION OF VARIOUS EQUIPMENT FROM OTHER FACILITIES AND THE COORDINATION OF INFRASTRUCTURE TO SUPPORT THE EQUIPMENT.

Manufacturing
  • Status: Complete
  • Sq. Ft.: 11,400
  • Duration: 10 Months
  • Project Delivery Method: GC/CM
  • Contract Type: Guaranteed Maximum price

Nelson Irrigation Bldg #9

New construction of a large manufacturing warehouse which will house many large ovens that melt and mold plastic into sprinkler parts.

This pre-engineered metal building features structural steel mezzanines, (2) 10-ton bridge cranes, and small office and staff areas.

Manufacturing
  • Status: Complete
  • Sq. Ft.: 36,000
  • Duration: 13 Months of construction
  • Project Delivery Method: Design/Build
  • Contract Type: Cost plus with a GMP

TISPORT

Renovation of a vacant grocery store into a manufacturing facility allowing for a local business to expand. 

several Building systems required complete replacement to accommodate the new use.

Manufacturing
  • Status: Complete
  • Sq. Ft.: 69,045
  • Duration: 5 Months
  • Project Delivery Method: GC/CM